the bath's nearly completed in house 117
a look at the process...
Friday, April 15, 2011
Friday, April 8, 2011
Our plasterboard's going up fast
Next week is our last of this term & only another 4 to go after Easter so we're going to try and knock out the rest of the Gib fixing before the break.
Our Aqualine finally arrived - roll on wet areas
Our Aqualine finally arrived - roll on wet areas
Doors cut out in the hall, tricky ceiling up
WC: gs1 completed
What's wrong with this picture...
Taper to TOP!
Lounge ceiling completed 1st thing this week
Bedrm1 BL1- vertical fix
Bedrm3 BL1- great cut out
Friday, April 1, 2011
Interior Lining_getting onto the Gib
House 117 have completed their lounge ceiling and 116 have got underway...
CCB meterbox installation
We all flashed them, fitted them, they weren't all the same, but they all passed inspection
Friday, March 11, 2011
Cladding, Cladding, Cladding,
.....and up............finished & nailed off
the first 2 walls completed
the final gable end weatherboard being cut
the first 2 walls completed
the final gable end weatherboard being cut
...& up
Monday, March 7, 2011
Weatherboards - great progress!
...after establishing our datum one board (& 5mm) above the head flashing and many checks we marked off the positions of the tops of the weatherboards around the entire perimeter of the house
Now we're making great progress getting the weatherboards up:
....getting the boards level, flush to eachother, jointed tidily & in the correct positions, fixed at the correct height and in stunning plumb lines vertically and with all cuts stained..........
..........AND not wasting our weatherboards
Lots to remember, but everyone's doing a great job and enjoying this stage of our build
Now we're making great progress getting the weatherboards up:
....getting the boards level, flush to eachother, jointed tidily & in the correct positions, fixed at the correct height and in stunning plumb lines vertically and with all cuts stained..........
..........AND not wasting our weatherboards
Lots to remember, but everyone's doing a great job and enjoying this stage of our build
A review of our 1st three weeks back on site
We had 2 inspections to get ready for on day 2!- cavity & flashing
It was important to get on with the work on day to be ready for the inspector the next day.
We checked that the cavity system was completed
This diagram shows how any moisture is directed away from the building via the head flashings
we got our head flashings on and sealed with aluband, followed by vermin strip to seal the cavity around these areas.
...and when we finally got them: we siliconed the plastic flashing dams in place to make sure any water that may travel down the cavity or the weatherboards, onto head flashing would travel out and away from the building & not back into the cavity
...and yes check out the black stain coming off our hands and onto everything we touch_______nearly 3 months and still not dry!!!!! It's really important to keep cleaning that stain off the joinery: if we leave it on there the sun and time can stain the powder coat finish.
It was important to get on with the work on day to be ready for the inspector the next day.
We checked that the cavity system was completed
This diagram shows how any moisture is directed away from the building via the head flashings
we got our head flashings on and sealed with aluband, followed by vermin strip to seal the cavity around these areas.
...and when we finally got them: we siliconed the plastic flashing dams in place to make sure any water that may travel down the cavity or the weatherboards, onto head flashing would travel out and away from the building & not back into the cavity
...and yes check out the black stain coming off our hands and onto everything we touch_______nearly 3 months and still not dry!!!!! It's really important to keep cleaning that stain off the joinery: if we leave it on there the sun and time can stain the powder coat finish.
Subscribe to:
Posts (Atom)